Client: Siemens
Value: £4.5M
Project Description:
Enabling works associated with the construction of a new HVDC Converter station Project consisted of phased civils and enabling works, Lowbury’s scope was to clear the existing land of underground obstructions, in particular 2000m3 of heavily reinforced concrete, remove unsuitable surface material and form main future works compound and formation by placing approx. 250,000m3 of material around required areas of site, key task also include compacting placed material using a dynamic compacting machine and subsequently testing the compaction. The site had trace elements of asbestos and as such air monitoring was continually check.
Works Included:
Scope of works :
Site access was constructed by Lowbury and maintained at all times during the construction & civils process. All work were completed in line with client programme and incorporated into the overall project programme. Whilst onsite substantial additional work was added to our contract as a consequence Lowbury were retained onsite for over 2 ½ years.