Client: Northern Power Grid Limited
Value: TBC
Project Description:
Construction of Pillswood Farm 132/33kV substation on land adjacent to Creyke Beck 400/132kV substation for the connection of two 49MW Battery Energy Storage Systems (BESS).
Works Included:
The works comprised civil engineering construction of an access road,
Piling and ring beam for modular buildings,
The constructions of transformer bunds.
The electrical work will comprise duct installation and cable pulling, erection of transformers, disconnector, and switch room and control room.