Client: Northern Power Grid Limited

Value: TBC

Project Description:

Construction of Pillswood Farm 132/33kV substation on land adjacent to Creyke Beck 400/132kV substation for the connection of two 49MW Battery Energy Storage Systems (BESS).

Works Included:

  • The works comprised civil engineering construction of an access road,
  • Piling and ring beam for modular buildings,

  • The constructions of transformer bunds.

  • The electrical work will comprise duct installation and cable pulling, erection of transformers, disconnector, and switch room and control room.