Client: Northern Power Grid (NPG)

Value: 285k

Project Description:

The project is to complete construction works at the Northern Gas networks depot, for a new Battery House and control room.

Works Included:

  • Ground works installation of sheet piles as temporary works to support the existing sloping contours.
  • New substation building will be a traditional construction blockwork inner, and brickwork outer leaf
  • Truss roof
  • Stepped foundations.
  • Installation of concrete retaining walls
  • Reinforced concrete ground bearing slab.
  • Installation of cable troughs.
  • Installation of ducting & draw pits.
  • Installation of drainage systems